Friday, April 26, 2013

The Risk Management Processes


The Practice Standard for Risk Management actually covers the same set of processes that you could find in the PMBoK but there is a subtle difference. The PMBoK is all about Inputs, tools & techniques and outputs. Whereas, the Practice Standard adds more than just that, it adds a lot of details that you wouldn’t find in the PMBoK guide.

Ok, the six risk management processes that are part of the PMBoK Guide and the Practice Standard have been covered in great detail in our blog in the preceding sections. But, let us quickly summarize what the Practice Standard has to say about those processes.

1. Plan Risk Management – Define the Scope and Objective of Project Risk Management knowledge area and ensure that risk processes are fully integrated into wider project management.
2. Identify Risks – Identify as many known risks as practically possible
3. Perform Qualitative Analysis – Evaluate the key characteristics of individual risks so that they can be prioritized for further action
4. Perform Quantitative Analysis – Evaluate the combined risk on the overall project
5. Plan Risk Responses – Determine response strategies and actions for individual & overall project risks and integrate them into a plan
6. Monitor and Control Risks – Implement the approved response strategies, review changes, identify additional risk management actions required and assess the effectiveness of overall risk processes

Lastly, the Practice Standard mentions something that we have gone over multiple times. It says that the risk management processes are iterative and dynamic in nature. They must be tailored to suit the needs of your respective projects.

This wraps up all the articles in the series on PMI-RMP Exam Preparation. All the very best for your Exam. You can view the whole series in the Index Page by clicking here.

Prev: Risk Management Foundation

Friday, July 6, 2012

Section Summary – Identify Risks



In this section we took a detailed look at one of the key activities in project risk management which is “Risk Identification”. Let us quickly summarize what we have learnt so far:

• The purpose of the risk identification process is to identify all possible risks that can affect our project
• The outcome of this step is the Risk Register
• Documents and artifacts that contain details reg. the project are one of the key inputs to this process along with the Risk Management Plan which outlines how we are going to conduct this activity
• Uncertainties are sources of risks and in this step we are going to analyze every aspect of the project to uncover those uncertainties
• There are 7 different tools & techniques that we can use in this risk identification process. They are:
o Documentation Review
o Information Gathering Techniques
o Checklist Analysis
o Assumptions Analysis
o Diagramming Techniques
o SWOT Analysis and
o Expert Judgment
• Information Gathering Techniques include – Brainstorming, Delphi technique, Interviewing and Root cause analysis
• Diagramming Techniques include – Cause & Effect diagrams, flowcharts, influence diagrams etc.
• SWOT Analysis intends on analyzing our project from the different perspectives like Strengths, Weaknesses, Opportunities and Threats to widen the reach of risk identification
• The 7 basic tools of quality are not directly part of the PBMOKs list of tools that we can use in risk identification but they are very relevant both from proper risk management perspective as well as the RMP Examination perspective
• These 7 basic tools of quality are:

1. Cause & Effect Diagrams
2. Control Charts
3. Flow Charts
4. Histograms
5. Pareto Charts
6. Run Charts and
7. Scatter Diagrams


Prev: Other Tools & Techniques

Next: Overview of Risk Communication

Friday, June 22, 2012

Inputs Used in the Risks Identification Process

The Identify Risks process is all about figuring out all possible uncertainties or problem areas that may come to bite us in future. So, to ensure that we figure out all possible problems we need to look at a variety of project related areas. All these put together are known as the “Inputs” to the Risk Identification process.

Inputs Used in the Identify Risks process

We have successfully entered the Identify Risks process. This is where we are going to take a look at all possible inputs that can help us identify all possible risks that may affect us. We will be looking at every nook and cranny of our project to uncover as many risks as possible.

Trivia:
The 4th edition of the PMBOK Guide is the latest and we will be using the same in all our studies. If you have an older version of the PMBOK guide, the names of the processes or the inputs/outputs may be different. As both the exam as well as this blog is based on the 4th edition of the PMBOK guide, I suggest you upgrade to the same. If you are a PMI Member a soft copy of the 4th edition is available for download as a member benefit. Alternately you can even order a paper-back copy from PMI website or Amazon.

The following are the items that we will need while Identifying Risks:

1. Enterprise Environmental Factors
2. Organizational Process Assets
3. Risk Management Plan
4. The following documents/plans from the Project Management Plan
a. Cost Management Plan
b. Scheduled Management Plan
c. Quality Management Plan
d. Scope Baseline
5. Activity Cost Estimates
6. Activity Duration Estimates
7. Stakeholder Register
8. Other Project Documents like
a. Work Performance Reports
b. Earned Value Reports
c. Assumptions Log
d. Baselines
e. Network Diagrams
f. Etc.

As we saw in the chapter on “Managing Uncertainty” Uncertainties are sources of risks and they can exist anywhere in our project. The list above is basically a “Where” we will be looking for all those uncertainties that exist in our project so that we can address them appropriately. Let us now take a detailed look at each of these items.

A word of Caution:
It is never a good idea to memorize stuff blindly, esp. for certifications like the RMP that test our practical knowledge and understanding of Project Risk Management concepts. So, take your time, read and understand what each item is and why it is used. This way you will not only be a better risk manager, but also eliminating the need to memorize stuff.

1. Enterprise Environmental Factors

We have learnt what these enterprise environmental factors are many times in this blog. The factors that are relevant in our identifying risks area are:
a. Commercial Databases
b. Public & Industry studies

2. Organizational Process Assets

These again have been covered many times. The organizational process assets include files & data from previous projects. We can study what the actual risks were, the responses that we used and the actual outcomes of the responses. We can utilize this information to ensure that we do not commit the same mistakes as our predecessors. Looking at the lessons learned documents from previous similar projects would be a good idea too. Document Templates also come under this section.

3. Risk Management Plan

As you may have guessed correctly by now, the risk management plan comes as an input to every risk management process in our project that happens after it is created. As this document explains how risk management activities are to be carried out in our project, it is an indispensable resource. We will be using the following from the risk management plan:
a. Assignment of Roles & Responsibilities
b. Budget and Schedule provisions & allocations to Risk Management activities
c. Risk Breakdown Structure


4. Artifacts from the Project Management Plan

The following artifacts from the Project Management Plan will be useful for us in this step. An important point here is that, you need not remember all intricate details about these processes like inputs, tools & techniques, outputs etc. (like what we were forced to remember for the PMP Exam). But, you need to understand these items in detail to ensure that you are able to correlate all those areas from these artifacts that can contribute to the projects risk management area.

a. Scope Baseline

The scope baseline includes the Project Scope Statement along with any constraints & assumptions. As you might already know, wherever assumptions are involved, there are bound to be uncertainties and it is these uncertainties that we are looking for. Also, constraints can be a major source of risks.

The scope baseline contains a key artifact that will be very useful for us from a Risk Management perspective. If you have already done your PMP you must have guessed this by now…

“Work Breakdown Structure”

A Work Breakdown Structure is going to give us a detailed perspective of the project work that will be done including tasks and sub-tasks. By going through this WBS thoroughly we can uncover a lot of potential risk possibilities.

b. Cost Management Plan

The Estimating Costs and Determining Budgets process of Project Planning creates the Projects Cost Baseline or in other words the Project Budget. The approach used in managing the project costs can be a major source of risks. For ex: a project that is operating on a tight budget with little room for maneuvering has a great risk of cost overruns. On the other hand, if the project has good cost reserves planned already, then the risks go down accordingly.

c. Schedule Management Plan

The Develop Project Schedule process creates the Project Schedule. By understanding the Projects Schedule and the Schedule Management Plan will give us a good idea of whether the project is operating on tight deadlines or has any slack in terms of completion dates. As in the case of Projects Budget, projects operating on a tight schedule can have a great deal of risk in terms of schedule overruns.

d. Quality Management Plan

The approach to quality management in the project has a direct bearing on the project risks. A Project where a great deal of importance is given to quality related activities to produce a good quality work product usually has lower risks when compared to one that does not follow good quality practices. In cases where the quality or work done is compromised (for whatever reason it may be), risks are introduced.

Poor Quality Standards is a major source of risks in many projects. If we address the Quality aspect of our project, we will be eliminating a good number of risks at its source.


5. Activity Cost Estimates

The Cost Estimates are created in the Estimating Costs process and these estimates can give us a good idea of the likely cost involved in all the scheduled project activities. This way we can identify if the project is in any danger of cost overruns.

6. Activity Duration Estimates

The activity duration estimates are created in the Estimate Activity Duration process. The quality and accuracy of the estimates can have a direct impact on the risks. If the estimate is accurate then the risks of schedule overruns are low whereas if the estimates are rough or ball-park then the chances of schedule slippages are pretty high which in turn means high risk.

7. Stakeholder Register

The stakeholder register gives us details about the list of all people who have a stake in our project. We can use it to identify the high influence group of stakeholders and handle them accordingly. We can also use this document to invite all those important stakeholders to the risk related meetings to ensure that everyone is on the same page.

8. Other Project Documents

There are a whole bunch of other project related documents that can be sources of risks or risk related information. Some of them are:
a. Work Performance Reports – The output of the Direct and Manage Project Execution process
b. Earned Value Reports – The output of the Measure Project Performance process
c. Assumption logs
d. Baselines (Cost, Schedule and Scope)
e. Network Diagrams – Created during the Develop Project Schedule process
f. Etc.

If you see closely, the scope baseline was considered as a separate input entity just a few paragraphs ago and has been mentioned again as part of the general term “Baselines” along with the Cost and Schedule baseline. Also, the Schedule Management Plan & the Cost Management Plan were covered already as inputs in detail and their baselines are considered here. This should give you a fair idea of the fact that the golden triangle “Scope-Time-Cost” are the key sources of risks for the Project and need to be investigated & analyzed thoroughly in order to minimize risks and to enhance the chances of the Project’s Success.

Apart from all the above mentioned inputs, any other document or information related to the Project that can be a source of risk or that can provide insights that will help in project risk management can be considered as input to this process.

Prev: Intro to Risk Identification

Next: Tools & Techniques used in Risk Identification

Friday, June 8, 2012

Risk Management & the PMBOK Guide


Are you PMP certified? Or have you read the PMBOK Guide? If so, you would already know that Risk Management is one of the 9 Project Management Knowledge Areas. The Risk Management Knowledge area of the PMBOK Guide will be a valuable resource in your preparation for the Risk Management Professional certification exam. Our exam preparation will closely follow how the PMBOK guide covers Risk Management.

If you are not PMP certified yet or do not have a copy of the PMBOK guide, don’t worry. In my earlier series on the PMP Certification exam preparation, I have covered the area of Risk Management in great detail. If you go through the chapters on Risk Management there, you should have more than enough information to proceed with your RMP exam preparation…

Risk Management Processes – As Per the PMBOK Guide

As per the PMBOK Guide, the Risk Management Knowledge Area is split into 6 distinct processes. Below is a short description of those processes with a link to learn more details about it. Those links contain the details regarding each of these processes from the PMBOK’s Perspective. That will be the basis for us in understanding the details that we will be covering in future from the RMP Exam perspective. So, spend some time and go through those chapters so that you establish the minimum level of knowledge required to easily progress towards the RMP Certification Examination.

The Risk Management Knowledge area includes the following Processes:

1. Plan Risk Management – Risk management planning is the process used to decide how the risk management activities for the project at hand will be performed. You can learn more about this Plan Risk Management process by Clicking Here
2. Identify Risks – The Identify Risk Process is the process where we actually identify all those uncertain events that might affect our project or its outcome. You can learn more about the Identify Risks process by Clicking Here
3. Perform Qualitative Risk Analysis – This is the process where we assess the Probability of the Risk event occurring and the Impact of the same. At the end of this process we will have a prioritized list of risks that we need to analyze further. You can learn more about the Perform Qualitative Risk Analysis process by Clicking Here
4. Perform Quantitative Risk Analysis – This is the process where we take the prioritized list of risks and apply mathematical analysis on them. You can learn more about the Perform Quantitative Risk Analysis process Clicking Here
5. Plan Risk Responses – This is the process where we will be deciding how we are going to handle the risks identified & analyzed in the previous processes if they occur. You can learn more about the Plan Risk Responses process by Clicking Here
6. Monitor & Control Risks – This is the process where we monitor the identified risks and identify & respond to new risks as they appear. You can learn more about the Monitor & Control Risks process by Clicking Here.

The whole Risk Management activity progresses step by step through these 6 processes. This is exactly how this blog is structured too. An important point to note here is that, the output of each of these processes serves as the input to the subsequent process. We will start with Plan Risk Management and progress towards Monitor & Control Risks…


The Risk Management Plan


The Risk Management Plan is the heart of our Risk Management activity and it is the artifact based on which we will be taking up each and every activity of Risk Management. The Risk Management Plan (we will call it RM Plan going forward) is a component of the Project Management Plan. We will be using the following as inputs to create the RM Plan:
a. Cost Management Plan
b. Schedule Management Plan
c. Communications Management Plan
d. Project Scope Statement
e. Organizational Process Assets &
f. Enterprise Environmental Factors

Don’t worry if you think I haven’t given much detail about the RM Plan creation here because there will be a whole section dedicated to it in future…

Key Inputs & Outputs of these Risk Management Processes

The RM Plan is the key output of the Plan Risk Management Process. As outlined in the previous paragraph on the Risk Management processes, the Identify Risks process takes this RM Plan as input and creates the Risk Register as the output. Each of the subsequent processes will take this Risk Register as input and then add or update it with more details and pass it on as input to the next process. This means that the Risk Register is going to be updated multiple times as it goes from Identify Risks to the Monitor & Control Risks process.

Along with the Risk Register, the Monitor & Control Risks process also uses Performance Reports (from the Report Project Performance process) and the Work Performance Information (from the Directing and Managing Project Execution process) that are created during the general Management of the Project. Also, any changes that may be suggested as output of this process will be submitted and put through the Perform Integrated Change Control process.

Prev: What is Project Risk?

Next: Understanding the Project Environment

Thursday, June 7, 2012

Risk Analysis

Risk Analysis is by far the most important domain of Project Risk Management. So, it is no big surprise that this domain will contribute 30% of questions in the RMP Examination. This is the largest of the domains in the Risk Management Framework in terms of contribution to the exam questions. To recap the exam objectives of Risk Analysis are:

a. Identify Risks
b. Evaluate Risks using Quantitative & Qualitative Risk Analysis
c. Prioritize Risks
d. Establish Control Limits

In order to plan effectively for the risks, we need to first analyze them properly. The Risk Analysis domain gives us all the inputs we need in order to plan the risk responses for the event that the risk occurs.

Logically thinking, it makes a lot of sense to spend our time and effort on risks that have the highest probability of occurring or on risks that have the highest potential impact on our project. Doesn’t it?

How will we identify which risk has a higher probability or a higher impact when compared to others? This is exactly what the Quantitative & Qualitative Analysis aspects of Risk Analysis will help us with. Before we begin our analysis, we need to identify all possible risks that may occur. By analyzing these risks and by understanding our stakeholder risk tolerance levels, we can shortlist and arrive at the important (or high priority) risks that we need to concentrate on…

You might be wondering what this “Establish Control Limits” objective is doing in the Risk Analysis domain. Are you? Setting these control limits is also part of the Risk Analysis Domain. We set these control limits by analyzing the risk tolerance levels of our stakeholders. The Project Management Team will use these limits to monitor the risks and to implement the planned responses. So, it makes perfect sense to include this objective as part of this domain…

In order to conduct an efficient Risk Analysis we need:
1. Good Information Gathering Techniques
2. Ability to Understand and Utilize Historic Information
3. Tools and Techniques to perform Qualitative Analysis
4. Tools and Techniques to perform Quantitative Analysis
5. Good Decision Making Capabilities
6. Ability to Perform Stakeholder Sensitivity Analysis

If all these things are not too clear and are making you nervous, don’t worry… This is just the initial introduction chapter. We will be covering the Risk Analysis Domain in great detail until you understand it clearly.

Prev: Risk Communication

Next: Risk Response Planning

Tuesday, December 13, 2011

Chapter 18: Risk Management


Aim: To understand the following Risk Management Processes
• Plan Risk Management
• Identify Risks
• Perform Qualitative Risk Analysis
• Perform Quantitative Risk Analysis
• Plan Risk Responses

If you have read the PMBOK or my earlier series “PMP Certification - Study Guide” you would by now know that

“A Risk is an Uncertain Event that can affect your Project”

Remember that this risk can be either Negative (An Actual Risk) or Positive (An Opportunity).

PMI’s risk management philosophy is based on a proactive approach to preventing negative risks and enhancing positive risks. Key points that you must remember about risk are:
• Risk can be either positive or negative. Positive risks are opportunities; negative risks are threats.
• A risk breakdown structure (RBS) is used to organize risk in a hierarchical structure.
• Monte Carlo analysis is a technique using simulations and probability in determining quantitative risk analysis.
• Risk categories are important in classifying risk.
• Probability and impact are both needed to assess risks.
• Quantitative analysis is generally reserved for high-probability, high-impact risk.
• Risk management planning and risk response planning are not the same activities.
• Risk identification is an iterative process that is performed throughout the project, not just during planning.
• Decision tree analysis is a technique using probabilities and costs for structured decision making.
• Five of the six risk management processes are conducted during the planning process group.
• The risk register is an important tool for capturing and tracking risks.

Exam Watch:
Risk register is a term introduced by PMI for the document detailing information on risks. The risk register includes all identified risks, the impacts of identified risks, proposed responses, responsible parties, and the current status.
Risk Management Planning and Risk Response Planning

The first step in Risk Management is to plan how we are going to conduct the whole Risk Management exercise in our project.
The risk management plan includes the risk methodology, roles/responsibilities, budget, execution timing, and definitions for risk categories, probabilities, and impacts. It is a summation of how the project team will carry out the remainder of the risk management activities for the project.

Exam Watch:
The risk management plan is not the same as the risk response plan. The Risk Response Plan will contain the possible actions you must take when a risk actually happens whereas the Risk Management Plan is the overall approach to managing Risks in the Project.

The risk management plan is the single output of the plan risk management process. The table below shows the inputs, tools and techniques, and outputs for the plan risk management process.

Plan Risk Management
Inputs Tools & Techniques Outputs

Project scope statement
Cost management plan
Schedule management plan
Communications management plan
Enterprise environmental factors
Organizational process assets

Planning meetings and analysis
Risk management plan
To know more about the Plan Risk Management Process Click Here

Risk Breakdown Structure (RBS)

A risk breakdown structure (RBS) is a tool that can be used to organize risks in a hierarchical fashion. The structure is defined using the risk categories. Even if an RBS is not used, risk categories are still defined in risk management planning. Risk categories can include
• Technical - Risk associated with using new technology.
• External - Risk associated with forces or entities outside the project organization. External risks can include external suppliers, customers, weather, and market conditions.
• Organizational - Risk associated with either the organization running the project or the organization where the project will be implemented.
• Project Management - Risk associated with project management processes.
Note that this is just a high level classification of Risks and you need to tweak this whole process to suit your needs in the Project that is being executed.

Risk Probability and Impact

Probability can be defined as the likelihood that a risk will occur. It can be expressed mathematically or as a relative scale (low, medium, high).

Impact is the effect a risk has if it actually occurs. It can also be defined on a relative scale or mathematically.

The team documents in the project management plan detail how probabilities and impacts are measured. For example, a red/yellow/green scale might be used, where high-probability, high-impact risks are red; low-probability, low-impact risks are green; and so on. Again, I repeat, how the risks are categorized and prioritized will vary based on the Project at hand and there is no Universal Rule as to how you must handle risks.

Exam Watch:
Both probability and impact are mandatory for evaluating risks. Think of it this way, how will you prioritize a risk if you do not know what the chances are of the risk happening and what the impact it would have if it occurs.

Risk Identification, Analysis, Response Planning, and Monitoring/Controlling

In the risk management process, completing the risk management plan is the first step. After the plan is in place, according to PMI the next steps in the risk management process are
• Risk Identification
• Risk Analysis (qualitative and quantitative)
• Risk Response planning
• Monitoring/controlling Risks (This is not in scope as part of this chapter on Planning. We will cover it in the chapter on Monitoring & Controlling)

Identify Risks

The identify risks process determines the risks that might affect the project and characterizes those risks.
Obviously, you need to identify all the possible risks that might affect your project if you are to have any success handling them. Isnt it? Keep in mind that identifying risks is not just the project manager’s responsibility; team members, subject matter experts, customers, stakeholders, and others are involved in this process.

The table below shows the inputs, tools and techniques, and outputs for the identify risks process.

Identify Risks
Inputs Tools & Techniques Outputs

Risk management plan
Activity cost estimates
Activity duration estimates
Scope baseline
Stakeholder register
Cost management plan
Schedule management plan
Quality management plan
Project documents
Enterprise environmental factors
Organizational process assets

Documentation reviews
Information gathering techniques
Checklist analysis
Assumptions analysis
Diagramming techniques
SWOT analysis (Strength, Weakness, Opportunity, Threat)
Expert judgment
Risk register
The Risk Register

The risk register is the output of the identify risks process. The risk register contains the following information:
• Risk description
• Date identified
• Category
• Potential responses
• Current status

Exam Watch:
Identify risks is not a one-time event that occurs just during the planning process. It should be conducted throughout the project, including when major milestones are reached and when an actual risk event occurs.
To know more about the Identify Risks Process Click Here

Qualitative and Quantitative Risk Analysis

Qualitative risk analysis provides further definition to the identified risks in order to determine appropriate responses to them. The key terms are probability and impact. Probability is important because it measures how likely a risk is to occur. A high-probability risk deserves more attention than a low-probability risk. Similarly, impact is a measure of how the risk will affect the project should it occur. A risk with low impact has a different response than one with a high impact.

Exam Watch:
Qualitative risk analysis is most concerned with ranking or prioritizing risks. It is used to determine which risks pose more of a potential effect on the project.

Qualitative risk analysis quickly prioritizes risks in order to conduct response planning and quantitative risk analysis, if required. Using the probability of the impact and a probability impact matrix, the project manager develops a prioritized list of risks. The output to this step is captured in the risk register.

The table below shows the inputs, tools and techniques, and outputs for the perform qualitative risk analysis process.

Perform Qualitative Risk Analysis
Inputs Tools & Techniques Outputs

Risk register
Risk management plan
Project scope statement
Organizational process assets

Risk probability and impact assessment
Probability and impact matrix
Risk data quality assessment
Risk categorization
Risk urgency assessment
Expert judgment
Risk register updates
To know more about Qualitative Risk Analysis Click Here

Quantitative risk analysis assigns numerical values to risks and looks at those risks that are high on the list of prioritized risks (The output of qualitative risk analysis). The goal of this process is to quantify possible outcomes for the project, determine probabilities of outcomes, further identify high impacting risks, and develop realistic scope, schedule, and cost targets based on risks.

The table below shows the inputs, tools and techniques, and outputs for the perform quantitative risk analysis process.

Perform Quantitative Risk Analysis
Inputs Tools & Techniques Outputs

Risk register
Risk management plan
Cost management plan
Schedule management plan
Organizational process assets

Data gathering and representation techniques
Quantitative risk analysis and modelling techniques
Expert judgment
Risk register updates
Exam Watch:
Quantitative risk analysis is more concerned with assigning each risk a numerical value. This value can then be used to figure out the relative impact that particular risk would have on the project.

To know more about Quantitative Risk Analysis Click Here

Planning Responses to Positive and Negative Risks

After all risks are identified, options to deal with the risks must be identified. Each risk is assigned to one or more owners to carry out the planned response. The responses are documented in the risk register after it has been updated in the plan risk responses process.

The table below shows the inputs, tools and techniques, and outputs for the plan risk responses process.

Plan Risk Responses
Inputs Tools & Techniques Outputs

Risk register
Risk management plan

Strategies for negative risks or threats
Strategies for positive risks or opportunities
Contingent response strategies plan
Expert judgment
Risk register updates
Risk-related contract decisions
Project management updates
Project document updates
There are four possible responses to negative risks:
• Avoid (Best) – Eliminating the Actual Threat by taking some action
• Transfer – Shifting the Risk to another party
• Mitigate – Take steps to ensure that the chances of the Risk happening are reduced
• Accept – Let the Risk happen. Use Contingency Reserves to handle it
For positive risks the responses include
• Exploit (Best) – Take steps to ensure that the Opportunity happens
• Share – Enlist the help of a Third party to capitalize on the opportunity
• Enhance – Taking steps to increase the probability of the Opportunity happening
• Accept – Take no steps to take advantage of the situation

To know more about the Plan Risk Responses process Click Here

Exam Watch:
Risks should be re-evaluated when the following events occur:
• A risk trigger is identified
• A change request is approved
• Key project milestones are reached
• Project phases end
• Deviations are detected in variance and trend analysis
• Corrective or preventive actions are implemented

Prev: Chapter 17

Next: Chapter 19
© 2013 by www.getpmpcertified.blogspot.com. All rights reserved. No part of this blog or its contents may be reproduced or transmitted in any form or by any means, electronic, mechanical, photocopying, recording, or otherwise, without prior written permission of the Author.