Friday, January 4, 2013

Risk Probability and Impact Matrix


In the previous chapter we took a detailed look at “Risk Probability & Impact Assessment” and assigned a risk rating to each of our identified risks based on the risk’s probability and impact. In this chapter, we are going to assign a risk score to our risk and categorize it as “High-Medium-Low” priority. This technique is called “Risk Probability and Impact Matrix”

Let us say, we are working a project to construct a new formula one race track in our country. It’s a high-profile and high budget project. During risk identification step, we found that, the supply of top quality “tar” that is used to lay the race track is of high demand and supply of the item could be a potential risk. Let us say that after analyzing our probability and impact definitions and stakeholder risk tolerance, our risk experts have assigned the following numbers to our risk:

Probability – 0.8
Impact – 0.64
As you can see, the numbers above are in cardinal scale (0 to 1) with numbers being closer to ‘1’ are of higher probability/impact when compared to numbers that are closer to ‘0’

This was done in our previous step so, what should we do next?

We are going to use the Risk Probability & Impact Matrix that is specific to our project. Look at the example below:


This matrix is combining the probability and impact into one overall rating. This is different from the rating assigned in the previous step as well as the one that was assigned using the Probability & Impact Matrix tool (From the RM Plan).

So, in order to minimize confusion, we will be referring to this rating as the “Risk Score” that signifies the combined probability and impact score of the risk under consideration with respect to our project objectives.

If you see the image closely, the probability is on the left going top to bottom, gradually reducing from 1 (a 100% sure shot possibility) towards 0. Similarly, the Impact is on the top going left to right, gradually going up from 0 (no impact) towards 1. The values in the table cells below are just the multiplied value of the risk probability and impact which we are going to consider our Risk Score. The values in each row refer to the impact score corresponding to the probability value.

Go back to the beginning of this chapter and see what numbers were assigned to our “Supply of TAR” risk? Now, look at the previous image (the matrix) and try to find out the cell where our probability and impact numbers match. If you found it very good. If you couldn’t, don’t worry, the cell is highlighted below just for you:


In our matrix, the “RED” color signifies High risk; “YELLOW” signifies Moderate risk and “GREEN” signifies Low risk. Unfortunately our risk “Supply of TAR” falls in the high risk category which means it has to be monitored closely to ensure that there is minimal impact on our project objectives.

An important point to note before we wrap up is the fact that, the above matrix is just an example for illustration purposes. Each organization could have a template for this and so, you must take a look at your organizational process assets to understand your org’s preferred way of assessing risks.

Prev: Risk Probability & Impact Assessment

Next: Risk Data Quality Assessment

Risk Probability and Impact Assessment


In the previous chapter, we saw an overview of all the tools and techniques that we could use as part of the Qualitative Risk Analysis phase of Risk Management. I had also said towards the end of the chapter that we will be covering all of those tools one by one in the subsequent chapters. Well, here we are. This chapter is about the first in the list, namely “Risk Probability & Impact Assessment”

Risk Probability & Impact Assessment

Risk Probability & Impact Assessment provides us with the initial risk rating for each of the risks that we have identified so far. To arrive at this risk rating, we will be using the definition of risk probability and impact that we defined when the Risk Management Plan was created. Remember the chapter on Creating the Risk Management Plan or Contents of the Risk Management Plan?

Using the definitions from the Risk Management Plan we will determine two things that will help us assign these risk ratings to our risks. They are:
a. Determine the chances (probability) that each risk will occur &
b. Examine the effects of a risk on Project objectives if the risk were to materialize. The usual project objectives we will be worried about are Cost, Quality, Schedule etc.

An important point to note here is that, we will be analyzing/assessing both risks and opportunities at this stage. Did you forget all about Objectives? It is easy to forget about Objectives whenever we get into topics on risk management. But, a good risk manager will always keep his eyes open for objectives and capitalize on them as and when possible.

Who is Involved in this step – Risk Probability & Impact Assessment?

This is a pretty straight forward question isn’t it? Try to answer this one by yourself…

Did you say “Everyone in the Project”?

If so, you are almost right. All team members from your projects take part in this step. Along with your project team members, knowledgeable individuals from outside the team known as “Risk Experts” too are part of the team. Practically speaking, you may not have the luxury of having risk experts as part of each project team. The organization as a whole may have a pool of risk experts who are shared between multiple projects as and when required. This is how a majority of the organizations function and we are going to assume that ours too does the same way.

Usually, this whole step is performed in a meeting. The project team and the Experts analyze each risk using the probability and impact definitions and then arrive at a risk rating.

Trivia:
Evaluation or assessment of risks is very subjective. The experts will be evaluating risks based on our projects risk tolerance as well as the probability & impact definitions provided to them. This information we (as project managers) provide these experts is extremely important because, without a proper understanding of our project as well as stakeholder risk tolerance, the experts can in no way perform good assessment. So, the onus is on us as project managers to understand stakeholder risk tolerance correctly and share that information with these risk experts so that they can utilize them effectively during risk analysis.

Not all risks will be assigned a rating. Only those risks that are high up in the probability & impact scales will be assigned a rating. The ones that are very low risk are usually moved into something called a “Watchlist”. These risks that are added to the watchlist are constantly monitored throughout the lifecycle of the project and will be taken up for re-assessment when its status changes. We put these low priority risks into the watchlist to ensure that we don’t totally forget them. If the status or key aspects of that low priority risk changes, we will typically re-assess it and assign a rating to that risk as well.

The Risk Ratings assigned in this technique will be used in the next technique in our list, “Probability & Impact Matrix” which we will be covering in the very next chapter.

Prev: Overview of Tools and Techniques for Qualitative Analysis

Next: Probability and Impact Matrix