Saturday, February 16, 2013

Decision Tree Analysis


In the previous chapter, we took a look at Expected Monetary Value or EMV Analysis. The Decision Tree Analysis is another tool/technique that we use in Quantitative Risk Analysis that directly uses this EMV Analysis. In this chapter, we are going to take a detailed look at Decision Tree Analysis

Decision Tree Analysis

Decision Tree Analysis is used to make decisions based on the risks that could impact us in the various possible scenarios we may encounter in future. It calculates the Expected Future Value of an activity based on the current impact & probability of all risks.

Decision Tree Analysis uses a Decision Tree Diagram. In the tree, we start at the starting point and go through the tree and take a decision based on the EMV for the Alternatives that are available for us. It shows a sequence of inter-related decisions and their respective EMVs so that you can take a good and properly thought-out decision. Decision Tree Analysis is used typically to take decisions dealing with Time or Cost.

Let us now take a look at some examples to understand Decision Tree Analysis:

Example 1:

Let us say, we are given the task of deciding between Vendor A and Vendor B. Vendor A has a Success Probability of 55% and an Impact of $ 70,000 while there is no impact on Failure. Similarly Vendor B has a 75% probability of Success and has an impact of $ 55,000 and he too has no impact on Failure. Based on this information, how would you choose the Vendor?

The simple Answer would be – Use Decision Tree Analysis. So, based on this question, if I were to create a Decision Tree, it would look like below:



So, here:

EMV for Vendor A: = 70000 * 55% = 38,500

EMV for Vendor B = 55000 * 75% = 41,250



Now, you know the EMV for each vendor. So, the wiser choice would be to choose Vendor B because the Expected Monetary Value of choosing Vendor B is greater than Vendor A.

Trivia:
If we had just considered the Impact, Vendor A would look like a better choice because he has a higher impact. But, he has a lower probability. So, Vendor B, even though has a lower impact, is selected because the combination of both probability and impact makes him the better choice.

Example 2:

Example 1 was an all positive scenario where there is no Impact for failure. What would you do in an all Negative Scenario?? Look at the Decision Tree Below:



In this example, in both cases, there is no impact if the outcome is a success. But, both Vendors A & B have an impact on failure and have a probability of failure too. So in this case, you may be wondering why I chose Vendor B instead of A, even though the EMV for A is higher. Are you???

In example 1, we were looking at positive EMV (For Success or Profits) so, we chose the vendor with higher profitable EMV. Whereas, in this case we are calculating Negative EMV (For Failure or Losses). So, choosing the vendor who would cause lower losses in case of a failure would be a better choice. Wouldn’t it??

Example 3: In examples 1 & 2, we took a look at trees that either had a positive or negative impact only. What must we do if we have both? Look at the tree below:



In this case, both Vendors A & B have Impact on both Success & Failure. So, the EMV for each vendor is the sum of the Individual EMV’s.

For Vendor A:

EMV for Failure = 1000 * 30% = 300

EMV for Success = 6000 * 70% = 4200

Total EMV for Vendor A = $ 4,500/-

For Vendor B:

EMV for Failure = -1200 * 40% = -480

EMV for Success = 7500 * 60% = 4500

Total EMV for Vendor B = $ 4,020/-

So, based on the total EMV, Vendor A is the better choice…

Trivia:
Did you note that Vendor B has a negative monetary impact in case of failure??? Be careful and note the – sign… If you did the calculation in a hurry and ignore the – symbol, your EMV for Vendor B would’ve been $ 4,980 suggesting that Vendor B is the better choice. Whereas, the truth was that, because of the –ve impact on failure, Vendor A is the better choice.
Example 4:

In all of the examples above, our decision was based solely on the impact and probability of the scenario’s outcome. What must we do in cases where the decision should also take into account the initial expenses incurred for the activity?

Let’s say, your company has grown hugely in the past couple of years and your current office does not have enough space to accommodate the new guys. So, now you have two choices – Either to construct/purchase a new office or expand the current premises to accommodate the newer guys. In either case, there is cost involved in completion of the office premises. Plus, there could be a high demand for the new space which results in high profits or there could be a low demand resulting in lower profits. This scenario is outlined in the Decision Tree below:




In Tree’s where an initial investment is present, we proceed just like the other scenarios wherein we calculate the EMV for each alternative and sum it up. After that, we deduct the Initial Expenses to arrive at the actual monetary value of the alternative.

Trivia:
In simpler terms, let’s say, I invest 5,000 rupees today and earn 10,000 after 6 months, my profit is 5,000 whereas, if I invest 10,000 rupees and earn 12,000 at the end of 6 months, my profit is only 2,000. Though the eventual money I get at the end of 6 months is higher in the second case, it also means that I invest a larger amount up front thereby reducing profits. So, option 1 where in invest 5000 and get 10000 at the end of 6 months is the better choice. Isn’t it?

So, the EMV Calculation works out as follows:



For Build:

Total EMV = 522,000

If we include Initial Cost – Net EMV = $ 292,000/-

For Expand:

Total EMV = 393,000

If we include Initial Cost – Net EMV = $ 298,000/-

So, the decision here would be to expand the current office premises. Even though the profits that we may earn if we move to a new office are higher, there is a higher impact if people are not willing to move and a high initial cost. As a result, the EMV of expanding the current office is more profitable and hence it is selected.


Some Important Decision Tree Related Terms:

For the exam, actually speaking, whatever we have covered so far is more than sufficient. But, for the same of completeness, I want to cover one last topic related to Decision Trees. There are 3 key terms that we will use while using Decision Tree’s in real life. They are:

a. Decision Node – The Point where an action or decision needs to be made – Signified by a solid black square
b. Chance Node – The Point where events that cannot be controlled by the person who is taking the decision happen – Signified by a solid black dot
c. End of Branch - The end point with nothing connected on one end – Signified by a solid tilted Triangle.

The sample Decision Tree below can help you understand better – as to what I am trying to convey here:



I repeat, knowing these terms or these symbols are not required for the Exam. But, we are not studying just to become certified. Our aim is to become better Risk Managers. So, knowing these will only help you perform your duties better…

Prev: Expected Monetary Value Analysis

Next: Modeling and Simulation

Friday, December 16, 2011

Chapter 19: Procurement Management



Aim: To understand the Plan Procurements process.

Procurement management involves the relationship between the buyer and the seller when products, services, or other results are being purchased by the project team in order to complete the project. Key PMI principles for procurement management are:
• The contract statement of work (SOW) is a key document that defines the work in order to allow buyers the ability to evaluate and bid on the work.
• There are three primary contract types:
o Fixed price
o Time and material
o Cost reimbursement
• The risk to both the buyer and seller depends on the type of contract chosen.
• The contract is a formal, written document and any changes are submitted in writing.

The table below shows the inputs, tools and techniques, and outputs for the plan procurements process.

Plan Procurements
Inputs Tools & Techniques Outputs

Scope baseline
Requirements documentation
Teaming agreements
Risk register
Risk-related contract decisions
Activity resource requirements
Project schedule
Activity cost estimates
Cost performance baseline
Enterprise environmental factors
Organizational process assets

Make-or-buy analysis
Expert judgment
Contract types

Procurement management plan
Procurement statements of work
Make-or-buy decisions
Procurement documents
Source selection criteria
Change requests
The Make or Buy Decision

The first step in procurement is taking the Make or Buy decision. This decision is made during the plan purchases and acquisition process. An analysis is done to determine if the product or service can be produced by the project team or if it should be purchased. This analysis might also include buying versus renting/leasing a product. For ex: Lets say in a construction company leasing a concrete mixer costs $500 per week to lease and $10,000 to buy, the company will take the decision on how long they intend on using the mixer. If they plan to use it for more than 20 months, then buying would be a wiser choice than leasing it out.

The Contract Statement of Work

In addition to making the make/buy decision during the plan purchases and acquisition process, it is during this step that the contract statement of work (SOW) is developed and the type of contract to be used is determined. The SOW is a document that defines the work to be performed. The contract SOW is developed from the scope statement and WBS and should be sufficiently detailed to allow the potential sellers to determine their ability to perform the work. A project can have multiple SOWs. The SOW will be the benchmark against with the work of the seller will be compared. The seller is liable only for all the work that is outlined in the SOW and nothing more. So, it is imperative that the SOW is complete in all aspects before the contract is signed.

Contract Types

A number of contract types are used in the procurement process. They are:
1. Fixed Price Contracts
a. Firm Fixed Price or Lump Sum (FFP)
b. Fixed Price Incentive Fee (FPIP)
c. Fixed Price with Economic Price Adjustment (FP – EPA)
2. Purchase Order
3. Cost Reimbursable Contracts
a. Cost Plus Fixed Fee (CPFF)
b. Cost Plus Incentive Fee (CPIF)
c. Cost Plus Award Fee (CPAF)
4. Time & Material (T&M)


From a buyer perspective the Fixed Price contracts are the least risky and Cost Reimbursable contracts are the most risky. From a seller perspective it is the other way round.

To know more about the different types of Contracts Click Here

The Procurement Management Plan

The procurement management plan is developed to describe how procurement activities will be carried out in the project. The plan can include content that provides guidance for
• Type of contracts to be used
• Risks and risk management issues
• Criteria for independent estimates
• Standard procurement documents and procedures
• Coordinating procurement with other projects and multiple vendors
• Project assumptions or constraints that affect procurements
• Handling procurement schedules
• Addressing make-or-buy decisions
• Identifying and managing performance requirements
• Identifying prequalified sellers
• Procurement metrics used to evaluate sellers and manage contracts

Exam Watch:
The steps of the procurement process are only necessary if the decision is made to buy outside resources. If the project decides to make it themselves, then the Procurement part is redundant and not required.

To know more about the Procurement Management Plan Click Here