Aim: To understand the Cost Estimation and Budgeting part of Project Management. The processes we will cover in this chapter are:
• Estimate Costs &
• Determine Budget
Estimate Costs:
The estimate cost process associates an expected cost of performing work to each activity. Cost estimates can include labor, materials, equipment, and any other direct costs for project activities. Based on the activity resource and duration estimates, the cost estimates express the cost, normally in monetary amounts, of completing the work of the project. As with all project documents, the cost estimates can change through the project as conditions change. Different events can cause the cost for any activity to go up or down and require the cost estimates for the project to change. The project manager has to ensure that the cost estimates are kept up-to-date to reflect the correct figures at all times.
The table below shows the inputs, tools and techniques, and outputs for the estimate cost process.
Estimate Costs | ||
---|---|---|
Inputs | Tools & Techniques | Outputs |
Scope baseline Project schedule Human resources plan Risk register Enterprise environmental factors Organizational process assets | Expert judgment Analogous estimating Parametric estimating Bottom-up estimating Three-point estimates Reserve analysis Cost of quality Project management estimating software Vendor bid analysis | Activity cost estimates Basis of estimates Project document updates |
• Analogous estimating - This uses actual cost values from similar activities. These activities can be from the same project or another project.
• Parametric estimating - This calculates cost estimates by multiplying the quantity of work or result of work. This type of estimate works best for standardized, and often repeated, activities. Ex: Laying a floor. Cost per tile + cost per hour of the workers pay can be used to arrive at the total cost of laying the floor.
• Three-point estimates - This uses three estimate values for each activity:
o Most likely - The cost most likely to occur• Bottom-up estimating - This technique calculates cost estimates by adding the costs of each individual work package. The technique starts at the most detailed level and rolls up the costs until a total cost for the project is obtained.
o Optimistic - The cost of the activity if everything goes as planned, or better
o Pessimistic - The cost of the activity in a worst-case scenario
After you know the costs to accomplish the work of the project, you can create the project budget. The determine budget process aggregates the activity cost estimates into a single document for the project. The resulting project budget expands on the preliminary budget from the project charter and provides far more detail.
The table below shows the inputs, tools and techniques, and outputs for the determine budget process.
Determine Budget | ||
---|---|---|
Inputs | Tools & Techniques | Outputs |
Activity cost estimates Basis of estimates Scope baseline Project schedule Resource calendars Contracts Organizational process assets | Cost aggregation Reserve analysis Expert judgment Historical relationships Funding limit reconciliation | Cost performance baseline Project funding requirements Project document updates |
Exam Watch:
Don’t confuse the estimate costs process with the determine budget process. The determine budget process aggregates all of the activity cost estimates to result in a budget baseline against which your project costs will be measured.
You can learn more about the Estimate Cost & Determine Budgets processes by Clicking Here
Prev: Chapter 12
Next: Chapter 14
No comments:
Post a Comment